Here are the areas GPA will be the next 7 days
Here are the areas Guam Power Authority will be the next seven days, according to their June 12, 2023 report.
Here are the areas Guam Power Authority will be the next seven days, according to their June 12, 2023 report.
Guam Power Authority has changed its daily progress report to reflect the names of streets crews will be working to restore over the next seven days. The relevant information follows,…
Merizo, Umatac, Inarajan, Piti, Toto, Yigo, Pagat, Yona, Dededo, Asan, OCP, Tamuning, and Hagatna – Guam Power Authority crews are coming to a neighborhood near you over the next three…
GPA officials, Speaker Therese Terlaje, and Sen. Will Parkinson receive the crew
Larger areas of Dededo, Tamuning, southern villages, and now Mangilao have been added to the list of areas Guam Power Authority crews will focus of restoring electricity to over the…
Crew from Washington arriving Thursday; 61 percent of system load restored; 43.3 percent of residential customers have power Guam Power Authority and Commonwealth Utilities Corporation crews aim to spend the…
Guam Power Authority has changed its daily reporting to differentiate between “System Load (Customer Demand) Restored,” which has reached 56 percent, and “Customers Restored,” a new reporting term. “System Load…
Guam Power Authority crews, with help starting today from 12 linemen from the CNMI’s Commonwealth Utilities Corporation, have restored power to 53.2 percent of customer demand, and energized 88.9 percent…
The Guam Power Authority is reporting that as of 1 p.m. Sunday, 49.2 percent of islandwide customer electricity demand has been restored. Twenty three of 24 critical substations have been…
CNMI Gov. Arnold Palacios and Lt. Gov. David Apatang prayed over and met today with the 12 professionals from the Commonwealth Utilities Corporation, who will be coming to Guam Sunday…